These clauses are in the contract because the employer wants them there. If there was no mechanism in the contract to extend time and a delay occurred which was the employer’s fault, or at least not the contractor’s fault, then time would be at large and the contractor would have a reasonable time to carry out his works. The employer would not be able to levy any liquidated damages.