Can an architect reduce the contract period to reflect omissions?

 

find out more

for expert advice on this topic, contact:
Philip Harris

related services

4. Can an architect reduce the contract period to reflect omissions?

In JCT 98, Condition 25.3.6:-

No decision of the architect under 25.3.2 or 25.3.3.2 shall fix a completion date earlier than the date for completion stated in the appendix. 

However, where an architect has granted an extension, in considering a further extension he can take into account omissions issued since granting the first extension.

25.3.1 – the architect shall in fixing a new completion date state the extent, if any, to which he has had regard to any instructions under 13.2 requiring… the omission of any work.