2020-02-17
Legal Articles

Practical completion: you'll know it when you see it

Home / Knowledge base / Practical completion: you'll know it when you see it

Posted by Stuart Thwaites on 01 July 2019

Stuart Thwaites Legal Director

Practical completion is one of those terms with which everyone is familiar – but for which there is no clear legal definition.  This point became the focus of attention in the case of Mears Limited v Costplan Services (South East) Ltd[1]a case which went to the Court of Appeal. Mears is a provider of managed student accommodation.

Circular definition of practical completion

The building contract in question was a JCT Design and Build Contract 2011 with bespoke amendments.  It defined the certificate of practical completion as “A certificate issued by the Employer’s Agent to the effect that practical completion of the Landlord’s works has been achieved in accordance with the Building Contract”.  That is a somewhat circular definition, as it does not tell the Agent how to work out when PC has been achieved so that the certificate can be issued. The dispute also involved an agreement for lease of the property.

The project concerned the design and build of student accommodation. The project fell into delay. A notice of late completion was issued, and Mears served a defects notice stating that 40 rooms had been constructed more than 3% smaller than required. Subsequently Costplan served notice that they intended to attend site to conduct a pre-completion inspection, “…with a view to issuing the certificate of practical completion.” Mears subsequently issued two further defects notices.

Can defects or breaches prevent issue of certificate of practical completion?

Mears made an application to court for an injunction to prevent Costplan from issuing the certificate of practical completion and seeking a number of declarations. The trial judge found that some of the rooms had indeed been constructed to the wrong size (too small) but refused to grant the injunction preventing issue of the certificate of PC.

Mears appealed to the Court of Appeal on that and a number of other issues.

The issue with which we are concerned for this article is whether the Employer’s Agent could certify PC where there are “known material or substantial defects”, or where there are “…material and substantial subsisting breaches…" of the agreement for lease relating to the performance of the works.

Practical completion is easier to recognise than define

The Court of Appeal reviewed the case law in relation to practical completion, none of which it found to be definitive/conclusive. Indeed the court recommended caution in relation to the case law.

Having reviewed the case law the court gave the following summary of the law on practical completion:

a)     “Practical completion is easier to recognise than define …. There are no hard and fast rules…

b)     The existence of latent defects cannot prevent practical completion... 

c)     In relation to patent defects, the cases show that there is no difference between an item of work that has yet to be completed … and an item of defective work which requires to be remedied.  Snagging lists can and will usually identify both types of items without distinction.”

Practical completion not necessarily hindered by irremediable breach or defect

In addition, even if a defect or breach is “irremediable”, that does not inevitably mean that practical completion has not been achieved.

Reference was also made, with seeming approval, to the leading construction textbook, Keating, that states that practical completion is “easier to recognise than to define.

As a result of those findings, the Court of Appeal rejected the declarations that were sought on appeal, and upheld the original Judge’s decision to refuse to grant the declarations that had been sought in relation to PC. The court had therefore been entitled to refuse to grant an injunction to prevent practical completion being certified.

The court also made clear that where a property is being built for habitation, the mere fact that it is habitable does not mean that it is practically complete.  

Although this case does provide some clarification in relation to practical completion, it nevertheless emphasises the fact that there remains no clear legal definition of that concept. As the judgement made clear “…in the absence of any express contractual definition or control, practical completion is, at least in the first instance, a question for the certifier”. The major standard form contracts such as JCT do not provide such a definition, but it remains possible to include a bespoke definition.


[1] Mears Limited v Costplan Services (South East) Ltd and others [2019] EWCA Civ 502

About the author

Stuart Thwaites

Legal Director

Stuart specialises in construction and engineering work in relation to resolving disputes and in the drafting and negotiation of contractual documentation.

Stuart Thwaites

Stuart specialises in construction and engineering work in relation to resolving disputes and in the drafting and negotiation of contractual documentation.

Recent articles

03 June 2020 Why use lawyers to draft your will or administer an estate?

In theory, drafting your own will using an off-the-shelf template, purchased online or from good stationers, can be a quick and easy way of leaving instructions on how you want your assets to be distributed after your death. Nonetheless, a will is a legal document and if it has been incorrectly worded and / or witnessed it may be invalid, meaning your estate would pass in accordance with the rules of intestacy (government provisions setting out how an estate should be divided if there is no will).

Read article
03 June 2020 Covid-19: a tour de force of force majeure?

In the following article, UK supply chain and logistics consultant, Paul Trudgian, and logistics law firm, Wright Hassall LLP, consider the impact of Covid-19 on the logistics industry. At the time of writing, we are now into week ten of lockdown and, by now, it is likely you will have read an article or two about the possibility of using force majeure to excuse non-performance of obligations due to Covid-19.

Read article
03 June 2020 Good markets hiding bad advice

Welcome to Wright Hassall’s podcast on “Good Markets Hiding Bad Advice”.

Read article
Contact
How can we help?
01926 732512
CALL BACK